Construction of the 10-mile Brooklyn Bridge Trail in the South Hills is expected to begin in 2027
The trail is planned to be built in two phases
- 2027Construction is expected to begin.
- Fall 2027First segment, Helena Ridge Trailhead to Brooklyn Bridge Trailhead, expected to be done.
- Fall 2028Remaining portion into Tucker Gulch is scheduled for completion.
Source: NBC Montana
If you hike or bike the South Hills, mark this one. Construction of the Brooklyn Bridge Trail is expected to begin in 2027, following nearly two decades of planning. The Montana Standard says Prickly Pear Land Trust, in coordination with the Helena-Lewis and Clark National Forest, is set to construct the "largest trail project in South Hills history" near Unionville.
The project recently cleared its final regulatory hurdles after the U.S. Forest Service addressed litigation involving the larger Tenmile South Helena project. The Helena Ranger District is Prickly Pear's partner on the build.
- Length: 10 miles, horseshoe-shaped and non-motorized
- Named for: a historic Unionville mine
- Also improves access for wildfire crews and emergency responders
- More info: pricklypearlt.org/brooklynbridge
$2 millionfundraising campaign for trail planning and construction
Prickly Pear Land Trust has launched the campaign to support the trail.
Source: NBC Montana